MAIN STREET, Downtown section: Downtown revitalization project includes replacement of sidewalks, watermains, storm mains, and repairs to sanitary mains. The limits of the project for 2015 are between Sackville Street and Ste-Anne Street. Construction is scheduled to begin in mid-August.
MAIN STREET: Installation of new bike lanes
BREAUX BRIDGE STREET: Reconstruction project between Alphonse Street and Providence Street. The work is scheduled to start in mid-May, and should be finished in mid-August 2015.
RIVERSIDE DRIVE: Replacement of riprap along the water and installation of guard rails.
ROTARY PARK: Installation of floating docks.
MULTIPURPOSE CENTER: Addition of a generator.
OLD TRAIN STATION, Belliveau Street: Renovations completed.
WATER SYSTEM: Replacement of the watermain under the Foch bridge.
TENNIS COURTS: Construction of 2 tennis courts behind the arena.
SKATE PARK: Construction of a new skate park.
TRAILS / BIKE LANES: Construction of a trail along Harper Street to join Sackville Street and Centenial Park (park behind the Vestiaire St-Joseph).
Equipment replaced in 2015:
½ ton truck
Lawnmower
Backhoe